Return to Scrapbook Home Page
Refer to Site Key and Floor Plans


Click here to see the previous set of pictures from July 1 to July 9, 1999.
Click on most images to see a larger version.



July 20, 1999

July 20 overview I returned after a week's absence to find the flat parts of the roof going on and many interior portions well on their way to being finished. I was invited to climb the ladder to get some pictures of the roofing process, but prudently declined.

framing for front lobby window
The other new feature visible in the shot above is the framing for the front "window." Given the Southern exposure of the front of the Downing Planetarium, the floor-to-ceiling windows once envisioned here would have fried the interior with solar energy. Instead we have a solid wall with this inset bay which will hold a long slit of glass with a colored square just four feet from the floor. The colored square will move along the floor with the Sun and will trace out time and date on the lobby floor. Stay tuned for more on this unique feature.

Mike Martinez is cutting drywall for installation in the West corridor.

catwalk and ducting

catwalk in place
Mike Wyllie, of Wyllie Construction, is shown at the right standing on the catwalk. He told me that all the interior carpentry work is essentially finished with the completion of the catwalk. The picture above shows how it is suspended by long threaded metal rods that extend all the way to special supports in the ceiling of the Planetarium.

more ducting in place drywall in West corridor
Much of the drywall has been installed in the West corridor. Work on the ducting for life support (heating and air conditioning for the less space-minded) continues, with major portions of it now in place. The picture to the right is a vertical composite showing the Resource Center on the North end of the building.



July 23, 1999

overview July 23 tarring the flat roof lobby window slit framed

The exterior shows that the edges of the room have had the shear panel added all the way around. Fresno Roofing continues to lay down the flat portions of the roof behind the parapet wall. The front slit window has been paneled in. Since this picture was taken around 9 am, the Sun has yet to make an appearance through the slit.

panorama of auditorium catwalk
Zumwalt and Horne inspect
The most dramatic inside change over the last two days has been the installation of the soundboard around the entire perimeter of the auditorium. If we had the dome in place, this space would start to look like the finished product. On the right, Kurt Zumwalt, the General Contractor for the Downing Planetarium, discusses construction progress with the Site Supervisor, Troy Horne.

ceiling insulation in Auditorium Nearly the entire ceiling of the planetarium has been covered with insulation. Today, more insulation is added to the walls inside the auditorium.

electrical conduit installed electrical detail

Work continues on the maze of wiring inside the planetarium. The solid metal conduit will hold power lines for lights and equipment. The plastic pipe will hold data, communications, telephone and speaker wires.

In the view of the Resource Room on the right, we can see the numerous power and data connections required to serve the computers that will be here. On the floor we can see the ladder that will lead up to the catwalk from this room.

behind the walls No building ever has enough storage space. This little odd-shaped room between the resource center and the auditorium will someday be crammed with stuff. I grabbed this shot to show what lies behind the walls.


July 26, 1999

overview July 26 finishing peak panelling

Fresno Roofing is just about finished with the flat part of the roof. In the telephoto shot on the right we can see the tar applied and some of the rolls of roofing material.

last natural light in the Auditorium As I entered the planetarium auditorium, I found I was just in time to record the last natural light to come into this area, except for the normal doors. The workers from Sacramento Insulation were about to install the remaining insulation at the lobby end of the auditorium.

lobby construction lobby curved wall
metal studs for lobby wall

The lobby area is still brightly lit by the two large openings at either end. These will eventually be glassed in. Westek Electrical is working on the electrical connections to the lobby while Burns Construction begins work on the drop ceiling.

In the picture on the right, we see (from top to bottom) Waraqa Howard, Andrew Michael, and Mike Martinez installing metal studs for the curved portion of the lobby ceiling.



July 28, 1999

overview July 28 After two days we see a few visible changes on the roofing job. (No, I haven't gone up the ladder to see what is happening behind the parapet.) We see some sort of facing on the wall beneath the roof on the East side of the building.

sheet rock in Audorium


sheet rock in Auditorium walls Yesterday and this morning the construction crew spent most of their time putting in a lot of sheet rock in the auditorium. Because this room in now all enclosed, construction lights have been strung. You can see all of the components of the inside of the wall in the picture on the right. First we have insulation, then sound board, then sheet rock.

work in the lobby more lobby work
When I arrived this afternoon, Mike, Andrew and Waraqa were back at work on the lobby ceiling. The curved portion had been completed two days ago. Today they were putting in the straight portions on the front (South) end of the lobby.


July 30, 1999

overview July 30 completing the flat roofs

As I arrived on the site about 10 am today, Fresno Roofing had completed the job and were cleaning up. By the time the picture on the left was taken, they had left the site. You can see the heavy grey composition roofing material that now covers the tar wash on the flat part of the roof. Rain from the peaked portion of the roof will gather in this area and then drain away through pipes down to the ground. The whole area will be inspected and leak tested in due course.

sidewalks and other flatwork To the West of the Downing Planetarium work has begun on the "flatwork." This includes the sidewalks and other concrete work that will surround the planetarium itself.

testing the plumbing fixing a leak

When I first walked into the planetarium this morning I was greeted by a puddle of water on the floor. They had just completed leak testing the plumbing, and a few joints needed some work. On the right Bill Schmidt of MJB Plumbing is making the repairs.

auditorium air handling Inside the auditorium and in the hall outside (inset) we see some more of the air handling system being installed.

lobby work Out in the lobby work continues on the metal studs for the ceiling. Sheet rock is also being installed on the walls.

lobby sheet rock


If you have any questions or comments, please send me an e-mail at david_zellmer@csufresno.edu.



To see the next set of pictures, go to August 1999, part 1.
Return to Scrapbook Home Page
Refer to Site Key and Floor Plans